Asia

India

Equipment was manufactured for a new Buffalo Slaughterhouse in Chandigarh in India. The complex has a capacity of 30 head per hour complete with freezing, chilling, boning and edible offal facilities. F.E.A. also provided a small bi-products plant which was custom designed to produce stock feed and fertiliser.

India

Manufactured, installed and commissioned 6 FEA Dehiders.

Indonesia – Sumatra

Extension and upgrade to extisting abattoir, including the design and manufacture of the Ritual Casting Box for Cattle.

Indonesia – Sumatra

Beef Slaughterhouse with a 200 head per day capacity with chilling and boning facilities.

Indonesia – Salatiga, Central Java

Manufacturing of a new beef slaughterhouse with a 30 head per hour capacity with freezing, chilling, boning and edible offal facilities.

Brunei – Bandar Seri Begawan

FEA tendered for this project to supply, install and commission an abattoir with the capacity of 30 – 100 head of beef per day. Both standard F.E.A. equipment and custom built pieces were provided to fit the consultant’s specific requirements.

Vietnam – Hanoi

Abattoir consisting of small stock processing for 480 head and 50 head of beef complete with chilling, boning and freezing facilities.

China – Tianjin

Completely designed, manufactured, installed and commissioned by Food Equipment Australia. This plant has been designed and built with all the new techniques required in a modern abattoir.
The plant has a capacity to process 600 sheep/goat per hour.

China – Xilinggolleagw, Inner Mongolia

Completely designed, manufactured, installed and commissioned by Food Equipment Australia. The plant has a capacity to process 400 sheep per hour.

China – Mengyang

Completely designed, manufactured, installed and commissioned by Food Equipment Australia. The plant has a capacity to process 600 sheep per hour.

China – Sijiqing

Completely designed, manufactured, installed and commissioned by Food Equipment Australia. The plant has a capacity to process 300 sheep per hour.

Bangladesh

Complete turnkey project including the design and supervision of construction. The project included a slaughter floor for beef with the capacity 300 head per day as well as 1500 head of sheep per day.

For more information please contact us.